西气东输四线天然气管道新疆段主体线路焊接完工
责任编辑:cnlng    浏览:225次    时间: 2024-04-01 12:46:03    | 来源:人民日报海外版   

免职声明:本网站为公益性网站,部分信息来自网络,如果涉及贵网站的知识产权,请及时反馈,我们承诺第一时间删除!

This website is a public welfare website, part of the information from the Internet, if it involves the intellectual property rights of your website, please timely feedback, we promise to delete the first time.

电话Tel: 19550540085: QQ号: 929496072 or 邮箱Email: Lng@vip.qq.com

摘要:西气东输四线天然气管道工程新疆段全线主体线路焊接完工,进入冲刺阶段,预计今年10月建成具备投产条件。工程建成投运后,年设计输送天然气150亿立方米、增输改造后可达300亿立方米,将有效提升我国天然气管网系统管输能力,提高能源输送的抗风险能力。The main line..

分享到:

西气东输四线天然气管道工程新疆段全线主体线路焊接完工,进入冲刺阶段,预计今年10月建成具备投产条件。工程建成投运后,年设计输送天然气150亿立方米、增输改造后可达300亿立方米,将有效提升我国天然气管网系统管输能力,提高能源输送的抗风险能力。

The main line of the Xinjiang section of the fourth line of the West-East natural gas pipeline project has been welded and entered the sprint stage, and is expected to be completed in October this year with the conditions for operation. After the project is completed and put into operation, it will be designed to transport 15 billion cubic meters of natural gas annually, and up to 30 billion cubic meters after the increase and transformation, which will effectively improve the pipeline transmission capacity of China's natural gas pipeline network system and improve the anti-risk ability of energy transmission.