国家能源集团召开化工产业3月份重大项目协调会
责任编辑:cnlng    浏览:493次    时间: 2024-03-26 10:20:54    | 来源:国际能源网   

免职声明:本网站为公益性网站,部分信息来自网络,如果涉及贵网站的知识产权,请及时反馈,我们承诺第一时间删除!

This website is a public welfare website, part of the information from the Internet, if it involves the intellectual property rights of your website, please timely feedback, we promise to delete the first time.

电话Tel: 19550540085: QQ号: 929496072 or 邮箱Email: Lng@vip.qq.com

摘要:会议充分肯定了化工产业重大项目推进取得的成绩,并就下一步工作提出要求。一是学习好领悟好贯彻好集团公司煤制油战略项目领导小组第一次会议精神,着力打造精品工程。二是加快完善化工产业“12469”基建管理体系,加强工作保障力度。三是压实化工公司在有关重大项目..

分享到:

会议充分肯定了化工产业重大项目推进取得的成绩,并就下一步工作提出要求。一是学习好领悟好贯彻好集团公司煤制油战略项目领导小组第一次会议精神,着力打造精品工程。二是加快完善化工产业“12469”基建管理体系,加强工作保障力度。三是压实化工公司在有关重大项目工艺技术和设计管理等方面的统筹归口职责。四是进一步落实项目业主责任制,把控好各项目关键节点,按照要求高质量完成节点任务目标,哈密化工、榆林化工要尽快做好项目管理总体策划。五是守好安全底线,保证基建项目有序推进。

会上,战规部和化工部分别通报了上期协调会督办、重大项目建设进展等情况及下一步工作要求,化工公司从工作机制调整后做好技术保障支持方面做了汇报,各项目单位汇报了督办问题落实、项目进展和下一步工作计划,总部相关部门对项目单位需要解决的问题进行了答复。

The meeting fully affirmed the achievements made in the promotion of major projects in the chemical industry, and put forward requirements for the next step. First, learn to understand and implement the spirit of the first meeting of the Group's coal-to-oil strategic project leading group, and strive to create high-quality projects. The second is to speed up the improvement of the chemical industry "12469" infrastructure management system and strengthen work security. The third is the centralized responsibility of compacting chemical companies in the process technology and design management of major projects. The fourth is to further implement the project owner responsibility system, control the key nodes of each project, complete the node task objectives in accordance with the requirements of high quality, and Hami Chemical and Yulin Chemical should do the overall project management planning as soon as possible. Fifth, observe the bottom line of security and ensure the orderly progress of infrastructure projects.

At the meeting, the War Planning Department and the Ministry of Chemical Industry respectively notified the supervision of the previous coordination meeting, the progress of major project construction and the next work requirements, the chemical company reported the technical support after the adjustment of the working mechanism, and the project units reported the implementation of the supervision problem, the project progress and the next work plan. The relevant departments at Headquarters responded to questions that needed to be addressed by the project unit.