中海新科环境承建山西五台山拐子沟生活垃圾填埋场综合治理(EPC)项目有序进行中
责任编辑:cnlng    浏览:353次    时间: 2024-05-27 10:05:49    | 来源:山东中海新科环境技术有限公司   

免职声明:本网站为公益性网站,部分信息来自网络,如果涉及贵网站的知识产权,请及时反馈,我们承诺第一时间删除!

This website is a public welfare website, part of the information from the Internet, if it involves the intellectual property rights of your website, please timely feedback, we promise to delete the first time.

电话Tel: 19550540085: QQ号: 929496072 or 邮箱Email: Lng@vip.qq.com

摘要:山东中海新科环境技术有限公司作为固废填埋场建设、修复、运维专家,积极承揽五台山拐子沟生活垃圾填埋场治理(EPC)项目。该项目总工期为14个月,于2024年4月动工,预计2025年6月完工,日前该项目正在稳步推进。该工程包括垃圾堆体整形工程,垂直防渗工程,渗滤液导..

分享到:

山东中海新科环境技术有限公司作为固废填埋场建设、修复、运维专家,积极承揽五台山拐子沟生活垃圾填埋场治理(EPC)项目。该项目总工期为14个月,于2024年4月动工,预计2025年6月完工,日前该项目正在稳步推进。

该工程包括垃圾堆体整形工程,垂直防渗工程,渗滤液导排工程,填埋气体导排处理工程,地表水导排工程,封场覆盖及生态恢复工程等。

该项目工程施工场地集中、狭窄,特别是堆体整形开挖、回填不均匀,运输不便,对此我们充分利用各地块作临时设施布置;该项目土石方工程量大,堆体整形开挖和回填直接决定工程进度和度汛安全,因此我们在开工后集中力量实施堆体整形防渗和调节池的施工,争取在主汛期雨季来临前完成施工;此外,该项目涉及水利、建筑、市政等多个专业,我们已配备相应的专业技术人员,把控好每一个专业细节,力求尽善尽美。

Shandong Zhonghai Xinke Environmental Technology Co., Ltd. as a solid waste landfill construction, repair, operation and maintenance experts, actively contracted Wutai Mountain Guazigou domestic waste landfill management (EPC) project. With a total construction period of 14 months, construction began in April 2024 and is expected to be completed in June 2025, the project is steadily progressing.

The project includes landfill body shaping engineering, vertical seepage prevention engineering, leachate drainage engineering, landfill gas drainage treatment engineering, surface water drainage engineering, site closure and ecological restoration engineering.

The construction site of the project is concentrated and narrow, especially the excavation and backfilling of the pile body are uneven, and the transportation is inconvenient, so we make full use of various blocks to arrange temporary facilities. The amount of earthwork in this project is large, and the excavation and backfilling of the pile body directly determine the progress of the project and the safety of flood control. Therefore, we concentrated on the construction of the pile body orthopedic anti-seepage and regulation pool after the construction started, and strive to complete the construction before the rainy season of the main flood season. In addition, the project involves water conservancy, construction, municipal and other professional, we have equipped the corresponding professional and technical personnel, control every professional detail, and strive to be perfect.


】【打印繁体】【投稿】 【收藏】 【推荐】 【举报】 【评论】 【关闭】【返回顶部