广西桂平航运枢纽扩机工程水轮发电机组进入安装高峰期
责任编辑:cnlng    浏览:150次    时间: 2024-03-27 10:15:58    | 来源:中国水利水电第十二工程局   

免职声明:本网站为公益性网站,部分信息来自网络,如果涉及贵网站的知识产权,请及时反馈,我们承诺第一时间删除!

This website is a public welfare website, part of the information from the Internet, if it involves the intellectual property rights of your website, please timely feedback, we promise to delete the first time.

电话Tel: 19550540085: QQ号: 929496072 or 邮箱Email: Lng@vip.qq.com

摘要:随着灯泡头吊装完成,广西桂平航运枢纽扩机工程水轮发电机组进入安装高峰期。此前,项目部已相继于2月1日完成定子叠片线下组装、3月5日完成厂房桥式起重机及桥式启闭机试重并通过验收、3月10日完成导水结构吊装。如今,项目建设现场一片“火热”。目前,项目基本实现..

分享到:

随着灯泡头吊装完成,广西桂平航运枢纽扩机工程水轮发电机组进入安装高峰期。此前,项目部已相继于2月1日完成定子叠片线下组装、3月5日完成厂房桥式起重机及桥式启闭机试重并通过验收、3月10日完成导水结构吊装。如今,项目建设现场一片“火热”。

目前,项目基本实现了厂房封顶,以及厂房外墙和副厂房内墙装修抹灰完成,项目部对穿坝段施工箱涵顶板混凝土,尾水渠围堰正在拆除施工中;导水机构已安装完成。副厂房一次、二次电缆正在敷设施工,大轴及轴承正在组装施工,其他设备安装工作也在有序推进。

下一步,项目部将严格按照既定并网发电目标,抢抓工程建设进度,全力协调施工队伍现场交叉、穿插施工,提高安装工作效率,全力以赴推进项目建设进度,确保如期实现机组并网目标。

With the completion of light bulb head hoisting, the expansion project of Guangxi Guiping Shipping Hub water turbine generator set entered the peak period of installation. Previously, the project department had completed the offline assembly of the stator stack on February 1, completed the test weight of the bridge crane and bridge hoist on March 5 and passed the acceptance, and completed the hoisting of the water guide structure on March 10. Today, the project construction site is "hot".

At present, the project has basically realized the capping of the plant, and the decoration and plastering of the external wall and the inner wall of the auxiliary plant have been completed. The project department is constructing the roof concrete of the box culvert in the dam section, and the tail canal cofferdam is being dismantled. The water guide mechanism has been installed. The primary and secondary cables in the auxiliary building are being laid, the major shafts and bearings are being assembled and constructed, and the installation of other equipment is also progressing in an orderly manner.

In the next step, the project department will strictly follow the established grid-connected power generation goals, seize the project construction progress, fully coordinate the construction team to cross and intersperse the construction site, improve the installation work efficiency, go all out to promote the project construction progress, and ensure that the unit grid-connected goals are achieved on schedule.