摘要:4月7日,经过项目部连续多日的准备,黄藏寺水利枢纽工程已完成进行人员入场安全培训、施工道路除冰、工作面整理、工器具准备,安全检查、设备检查等多项工作,标志着黄藏寺水利枢纽机电设备安装工程全面复工。进入4月,地处青藏高原的青海黄藏寺水利枢纽工程项目迎来..

分享到:

4月7日,经过项目部连续多日的准备,黄藏寺水利枢纽工程已完成进行人员入场安全培训、施工道路除冰、工作面整理、工器具准备,安全检查、设备检查等多项工作,标志着黄藏寺水利枢纽机电设备安装工程全面复工。

进入4月,地处青藏高原的青海黄藏寺水利枢纽工程项目迎来了每年的施工黄金季节,工地条件依旧艰苦,风雪交加,但是回到岗位的项目职工迎难而上,干劲十足。近日,进水口快速门、3号机转子、照明线路敷设、辅机管路等工作面施工已全面展开。

2024年,黄藏寺水利枢纽机电设备及金属结构安装项目主要进度计划是9月30日前完成所有机组调试、剩余工作量主要为三台机组安装、GIS设备、屋顶出线架、电气二次、溢流表孔工作门等安装工作。工期紧、任务重,项目部全体干部职工将团结一致,攻坚克难,确保2024年施工计划目标顺利实现。目前,项目部正在抓紧进行3号机组机械部分安装、表孔工作门安装、屋顶出线架等,各项施工任务有条不紊向前推进。

On April 7, after several consecutive days of preparation by the project department, the Huangzang Temple water conservancy project has completed a number of work such as personnel entrance safety training, construction road deicing, working face finishing, equipment preparation, safety inspection, and equipment inspection, marking the full resumption of the mechanical and electrical equipment installation project of Huangzang Temple water conservancy project.

Entering April, Qinghai Huangzangsi Water Conservancy Project located on the Qinghai-Tibet Plateau ushered in the annual construction golden season, the site conditions are still difficult, snow and snow, but the project staff back to work, full of enthusiasm. Recently, the water inlet fast door, No. 3 machine rotor, lighting line laying, auxiliary machine pipeline and other work surface construction has been in full swing.

In 2024, the main schedule of the mechanical and electrical equipment and metal structure installation project of Huangzangsi Water Conservancy project is to complete the commissioning of all units before September 30, and the remaining workload is mainly the installation of three units, GIS equipment, roof outlet rack, electrical secondary, overflow gauge hole work door and other installation work. Due to tight construction period and heavy tasks, all cadres and staff of the project department will work together to overcome difficulties and ensure the smooth realization of the 2024 construction plan objectives. At present, the project department is paying close attention to the installation of the mechanical part of the No. 3 unit, the installation of the table hole work door, the roof cable frame, etc., and the construction tasks are moving forward in an orderly manner.