印度尼西亚Julu水电站项目大坝施工成功实现二期转流
责任编辑:cnlng    浏览:272次    时间: 2024-04-15 10:20:45    | 来源:中国水电十六局   

免职声明:本网站为公益性网站,部分信息来自网络,如果涉及贵网站的知识产权,请及时反馈,我们承诺第一时间删除!

This website is a public welfare website, part of the information from the Internet, if it involves the intellectual property rights of your website, please timely feedback, we promise to delete the first time.

电话Tel: 19550540085: QQ号: 929496072 or 邮箱Email: Lng@vip.qq.com

摘要:印度尼西亚Julu水电站自2022年5月项目破土动工以来,水电十六局项目团队精心策划、周密组织,克服重重困难,确保工程按计划有序推进,关键项目节点一一如期目标,得到了工程业主的高度赞誉。截止目前,土建工作已完成主副厂房、引水隧洞、压力管道、尾水渠、运行管理..

分享到:

印度尼西亚Julu水电站自2022年5月项目破土动工以来,水电十六局项目团队精心策划、周密组织,克服重重困难,确保工程按计划有序推进,关键项目节点一一如期目标,得到了工程业主的高度赞誉。截止目前,土建工作已完成主副厂房、引水隧洞、压力管道、尾水渠、运行管理房等重要设施的施工,机电安装也已全面铺开。

随着大坝二期转流的成功实现,工程施工重点转移至左岸非溢流坝段的施工,同时,开关站、装修工程和附属工程的施工也正在有条不紊地推进中。

印度尼西亚Julu水电站位于印尼北苏门答腊省,安装2台机组,安装两台单机容量9兆瓦机组,总装机容量18兆瓦。工期26个月,缺陷责任期1年。这也是水电十六局继承建印尼阿萨汉1号水电站厂房系统工程后,在印尼承建的第二座水电站,对水电十六局进一步拓展东南亚市场具有重要意义。

Since the project of Julu hydropower Station in Indonesia broke ground in May 2022, the project team of Hydropower Bureau 16 has carefully planned and organized, overcome numerous difficulties, and ensured the orderly progress of the project as planned, and the key project nodes have been targeted on schedule, which has been highly praised by the project owner. Up to now, the construction of important facilities such as the main and auxiliary workshops, diversion tunnels, pressure pipes, tail canals and operation management rooms has been completed, and the mechanical and electrical installation has also been fully rolled out.

With the successful realization of the second phase of dam diversion, the construction focus has been transferred to the construction of the non-overflow dam section on the left bank. At the same time, the construction of the switch station, renovation works and auxiliary works is also being carried out in an orderly manner.

Indonesia's Julu hydropower station is located in North Sumatra province, Indonesia, installed 2 units, installed two single-unit capacity of 9 MW units, with a total installed capacity of 18 MW. The construction period is 26 months, and the defect liability period is 1 year. This is also the second hydropower station to be built in Indonesia after the construction of the Indonesian Asahan 1 hydropower plant system project, which is of great significance to the hydropower 16 Bureau to further expand the Southeast Asian market.